Robert Taylor - Electrical Consulting Engineer, Contractor and Electrician

Robert Taylor - Electrical Consulting Engineer, Contractor and Electrician

Menu

Installation

The project at the House of Flowers


On approval of my method statement and risk assessments the works took three days to complete.

The shop was kept open for business during the works, I installed barrier to section off each aisle during the removal of the large Fluorescent luminaires and installation of the new LED luminaires.

I reused the existing PVC conduit wiring system and drop chain fixings.

 

Additional works were carried out, removal of two lengths of track lighting, repair to ceiling fan and installing LED lamps to the Yankie Candle display unit and as there were installation cost savings, the project was completed for the budget price.


The installation was tested and commission to the satisfaction of my client and handed over on time and to budget.